
Upgrade of wheat starch production to 21T/Hr
RB Plant’s client’s, project was to increase the capacity of the Mill & Starch manufacturing facility to 240,000 tons of wheat grind/year with an annual operating capacity of 21t/hr of flour throughput.
SCOPE ▾
RB Plants initial role was to carry out a preliminary study to encompass:
- Detailed Process Schematics
- Process Layout
- Equipment & Line Capacities
- Numerical Catalogue of Project Tasks & activities
- Accurate Project Costs
- Project timescale & preliminary program
- Production Plan & Outage schedule
From the above RB plant was then tasked with the construction/installation of the plant & equipment to achieve the required processing improvement as listed in the next section.
THE CHALLENGE ▾
RB Plant main challenges were the following:
Flour Mill
- Install additional Satake Debranning Technology to increase mill capacity to 21t/Hr
Dough Preparation & Separation
- Install Flour Water mixer to Client’s standard
- Install Batter residence Loop
- Install Hydrocyclone separators to the Client’s “Pate Mole” standard
Gluten Drying & Milling
- Up rate gluten dryer feed system
- Install additional gluten dewatering equipment
- Up rate gluten milling system with standard Client’s Freres Mill
- Up rate existing dryers
- Install intermediate Starch slurry storage
- Upgrade Finished Product Storage & out load
Starch Refining Process
- Install additional fibre removal equipment to Client’s standard
- Replace current refining hydrocyclone system with Client’s standard
- Install QX separator equipment on secondary starch (A-) stream
Soluble Process
- Pipe work to be reviewed
- De-Bottleneck solubles evaporation stage
Utilities
- Replace the starch Provox system with Foxboro system
- Upgrade compressed air system
- Upgrade electrical distribution system
- Install additional boiler water treatment capacity
- Upgrade buildings & roads
All other work identified & defined by Pre-Project study
THE OUTCOME ▾
RB Group’s end result of all the works above was beneficial operation on time and within budget . Allowing for increase production capacity to begin on schedule.
THE BENEFIT ▾
RB Group’s main benefits to the client were through their increased processing capacity & plant throughput increase. Also, by updating their electrical & control systems better process control was achieved & reduced loses through better overall control of the plant