Upgrade existing facility to make new drug with OEL 1.5 µg/m³ 8-hour TWA

Upgrade existing facility to make new drug with OEL 1.5 µg/m³ 8-hour TWA

RB Plant was tasked with upgrading the existing facilities, equipment and utilities of a client who were looking to manufacture a new product on an existing plant. The scope of work involved included the following: HVAC upgrade to ISO14644-1 Standard 7, installation of new HTF package, Detailed Design, HAZOP, Costings & Procurement, Project & Construction Management, Validation. 

RB plant was to complete all work for the client within tight timescales and with minimal impact to existing production, MOC to be compatible with HCL – replace stainless steel filter with Hastelloy, and upgrade containment system to handle product of 1.5 µg/m³.

RB Plant delivered a staged installation project to meet the client’s needs.

Stage 1

Shutdown to relocate existing equipment & make space for new Facility.

Stage 2

Recommission existing equipment.

Stage 3

Install & commission new equipment.

Through RB Plant’s approach, the client’s requirements were met and the project was delivered on time & within budget whilst overcoming logistically difficult milestones.